DHBVN Net Metering: The Short Answer
Net metering lets your rooftop solar plant send extra units to the grid and take units back when the sun is down. A two-way meter records both, and your bill is worked out on the difference. In Gurgaon, DHBVN handles this, and the usual time from application to commissioning is 15 to 25 working days.
This guide is a checklist for homeowners. It does not repeat the full rules, which are in our DHBVN net metering guidelines, or the portal workflow in our DHBVN solar net metering process page. Use this post to get your papers, your timing and your questions in order before anyone files anything.
Who Applies, and When
The application is made against your DHBVN consumer account, so the applicant is the person whose name is on the electricity bill. In practice your installer fills in the online forms for you, but the details must be yours and they must be correct.
File at the start, not at the end. The feasibility check by the local DHBVN office comes before the plant is built, and the meter work comes after. If you wait until the panels are on the roof, you are waiting with a finished plant that cannot be switched on. If you also want the government subsidy, the net meter is one of its conditions, as our PM Surya Ghar online application guide explains.
Documents Checklist
Keep clear scans or photos of these ready. Your installer prepares the technical papers, and you provide the personal ones.
| Document | Why it is needed |
|---|---|
| Latest DHBVN electricity bill | Shows your consumer account number, sanctioned load and the name on the connection |
| Aadhaar or government photo ID | Proves who you are; the name should match the bill |
| Property ownership proof | Shows you have the right to put a plant on that roof (sale deed, allotment letter or recent property tax receipt) |
| Passport-size photographs | Go into the application file |
| Cancelled cheque | Needed for the subsidy payout to your bank account, if you are claiming it |
| Single line diagram and test reports | Prepared by the installer; show how the plant is wired and that the equipment is tested |
| Structural stability certificate | Confirms the roof and structure can carry the plant |
| Company papers, if the connection is a company one | Show who is allowed to sign for the business |
Names and addresses should read the same on every paper. That one habit prevents more delays than any other.
Steps and Who Does Each One
| Step | What happens | Who does it |
|---|---|---|
| 1. Load check | Your sanctioned load is compared with the plant size you want | Installer, with your bill |
| 2. Online application | Consumer account details and load go on the portal | Installer, with your consent |
| 3. Feasibility approval | The local DHBVN office checks the grid at your location | DHBVN |
| 4. Installation and test papers | The plant is built and the work completion papers are prepared | Installer |
| 5. Meter purchase and testing | A two-way meter is bought and sent to the DHBVN lab for testing and sealing | Installer coordinates, DHBVN tests |
| 6. Site inspection and meter change | DHBVN checks safety and fits the new meter | DHBVN |
| 7. Commissioning | The plant is switched on and starting readings are noted | DHBVN and installer, you present |
The portal may change its steps and screens from time to time, so treat this as a guide to the order of work, not as a copy of the screens.
How Long It Takes
Plan for 15 to 25 working days from application to commissioning. The feasibility approval is usually the longest single wait and is listed on our process page at 7 to 10 days. Home installation itself usually takes 7 to 30 days depending on roof, structure and approvals. These stages overlap, so the whole job takes less time than the three added together.
If you are claiming the subsidy, it usually arrives 30 to 45 days after commissioning and is paid by the government to your bank account. It is never guaranteed, so do not plan other spending around it. If you are financing the plant, see solar loan interest rates and EMI in Haryana for how the loan fits around this timeline.
Mistakes That Delay Net Metering
Most delays come from paperwork, not from the plant. These are the common ones, stated as general cautions.
- Name mismatch. The bill says one spelling, the Aadhaar card says another, the bank account says a third. Fix this before the application, not after a query comes back.
- Sanctioned load lower than the plant size. The plant capacity generally has to stay within your sanctioned load. If you want a bigger plant, ask for a load increase first.
- Pending dues. Unpaid electricity bills can hold up the application. Clear them and keep the receipt.
- Unregistered vendor. If you want the subsidy, the installer must be MNRE-registered. Ask for the registration number before you pay an advance.
- Missing signatures. A form with a signature missing is likely to come back with a query. Check every page before it is submitted.
- Wrong or unreadable scans. Cut-off edges and blurred numbers lead to avoidable queries.
For larger plants, the sanctioned load and the type of connection (single-phase or three-phase) matter more, so ask your installer to confirm both on your bill before quoting.
What Happens on Meter-Change Day
Your installer will tell you the day in advance. DHBVN staff come to the site, check the safety switches and earthing, remove the old meter and fit the two-way meter. The plant is then switched on.
Be present, and keep the bill and ID at hand. Ask for the starting import and export readings to be noted, and take a photo of the new meter display and its seal. Do not break the seal or move the meter yourself at any point.
An on-grid plant stops during a grid outage for safety, so net metering alone does not give you backup. If you want power during cuts, compare the options in on-grid vs hybrid solar cost in Gurgaon, or read about on-grid solar first.
Your First Bill After Net Metering
Do not judge the system by the first bill alone. Check these three things in general terms:
- Import units: what you took from the grid.
- Export units: what your plant sent to the grid.
- Net units: the difference, which is what the bill is based on.
If export is zero, or the readings look odd, call your installer with a photo of the meter and the bill. The credit and settlement rules are set by the regulator and may change, so for the exact treatment see the rules on our guidelines page and the current DHBVN notice rather than a general post like this one.
Next Step
If you are in Rohtak or Jhajjar, your discom is UHBVN, not DHBVN. The general order of work is the same, but check the local office for its own forms and steps. For Gurgaon and south Haryana, our team handles the DHBVN paperwork under our PM Surya Ghar solar installation service. Request a free site survey and we will check your bill, sanctioned load and roof before you commit.